Earlier this summer, we started site preparation activities that had to be planned and carefully sequenced due to environmental timing windows. As part of the activity to isolate the Kitimat River Side Channel that flows on the project site and divert a portion of Beaver Creek to allow dewatering, we had to salvage fish and amphibians.

Our contractor Haisla Triton Limited Partnership started fish salvage activity from July to November. The work is now complete and we’re extremely pleased the fish were salvaged from watercourses. Well done team!