CONSTRUCTION UPDATE: Over the summer, we started site preparation activities that were seasonally sensitive to ensure the project is delivered on schedule and cost. The work had to be planned and carefully sequenced because it’s affected by environmental timing windows. The work included berm (or embankment) construction and temporarily diverting a portion of Beaver Creek to allow dewatering of the project site.

We’re pleased to say that Beaver Creek is now flowing through our new diversion channel and converging with Anderson Creek. Water levels have risen substantially. With connection fully established, we’ll start to survey for spawning salmon. They’ll use our 500 metre-long channel to reach their final destination in the upper gravel beds of Beaver Creek. #LNG4Canada #LNG #Kitimat #BeaverCreek

Source

Conversations

No conversations yet